Skip to main content

Week 8 (03-14-18): Welding the Nuts on the bases & Pouring the Concrete into the Molds

During this week, the team met up a total of 3 times within the week, including the time spent on Wednesday. Throughout the week, I worked on what needed to be finished with the welding for the nuts and hot rolled steel flat bar. With 80+ welds to complete, I was able to work through the 17 bases that we needed welded through. Since the welds were completed, It was time to pour the remaining 17 bases in order to test them out and see how they perform under the given load and unevenness of the ground. We poured, mixed, stirred, condensed, and flattedned the concrete to fit the necessary molds. All we have to do is wait for next week in order to see how the concrete molds formed. I hope it is the same, if not better than the last three that we tested.



Comments

Popular posts from this blog

Week 13 (04-25-18): Cleaning up Welded Track Attachments

This week, I focused my efforts on cleaning up some of the welded sections that I worked on last week. Within the square tubing, there is a slight rise that follows along the length of the tubing. This makes it impossible for these parts to slide into the support sleeves that we have already made. In order to finish up these components, I filed them down with a combination of using a Dremel tool with a diamond bit tip and Spartan Superway's file. The first image shows the excess metal that protrudes out of the inside of the square tubing. The next image shows that same protrusion grinded down with the use of the Dremel tool and shop file.

Week 12 (04-18-18): Welding For Last Support Components

On Monday, the team met up and needed to address some of the issues that we had with the welder. Kevin was in constant communication with administration and Dan (from full-scale bogey) to ensure we were taking the correct course of action. Kevin and I took a trip to Praxair to retrieve a new tank of Argon for the remaining welds. After coming back and setting up the welder, I started and finished the welds necessary for the support structures. I encountered some issues during this process as I never found the correct way to properly weld these two components together due to the differences in thickness of the square tubing and the sheet metal. If I utilize too high of a current, the sheet metal would have a hole burnt through. However, if the current was too low, there would be no penetration of the square tubing. Even after completing 80 welds, this process was not mastered and still need to be cleaned up through other methods that will be looked into.

Week 14 (05-02-18): Finishing up the Supports & Putting the Track Together

Last week, I ground down the welded support parts that attach to the track. I finished 20 of these parts and it required a lot of patience since grinding down steel requires some time. I even had a collet for the Dremel tool break on me since the diamond tip Dremel-bit pushed the collet to open up throughout the duration of the grinding process. By trying to close up the collet to secure the bit, one of the collet's prongs broke. After these parts were completed, I started drilling holes into them to ensure that they would fit into the whole track assembly smoothly. I used the drill press and some of the brackets that Kevin finished printing. The end result of these components looks like the following image: After the support structures were put together, we assembled the track fully for the first time. Although it was a small assembly that reduced the length of the track, due to removing several straights, it allowed for the other subteams to test the bogey and controls....